Your TNA measured the shutdown, not the working year

Needs collected during a plant shutdown describe people who leave in a fortnight. Weight sampling by exposure hours across the production calendar and show what changes.

Rajendra Kumar · 26 November 2026 · 9 min read

Wide view inside a plant hall during a shutdown: scaffolding wrapped in stained dust sheets on the left, a bank of rusted insulated pipes and valve handwheels on the right, golden sun cutting through a high window.

Representational image.

Your TNA measured the shutdown, not the working year

The plant closes for annual maintenance in the second week of December. HR reads the calendar as a gift. Every shift is off, every contractor is on site, the conference room with the projector is free, and 700 people can be interviewed in nine days. The TNA finishes on schedule and the report is thick: weak permit-to-work discipline, poor isolation and lock-out practice, supervisors who cannot read P&IDs, no confidence in emergency response.

All of it is true, and almost all of it is about the shutdown.

Six weeks later the same plant runs with 160 operators and 40 maintenance fitters. The 640 contract workers in the report have gone to another state for another turnaround. The training plan built on that report spends the year preparing an audience that is not in the building.

This is not a data quality problem, and the fix is not a better questionnaire. The TNA sampled the state of the plant with the highest headcount and the lowest hours. The findings are a snapshot of an unusual fortnight, weighted as though it were the year.

A need is exposure multiplied by people, not people alone

Training needs are usually collected by availability. Whoever is present, in the largest group, in the most convenient room, gets asked. That produces a sample of attendance, and attendance during a shutdown is not attendance during the year.

The EIA's own description of the cycle is a useful corrective. Routine turnarounds on key refinery units are planned every three to five years and involve one to two years of advance planning. During a major unit turnaround, as many as 1,500 to 2,000 skilled contract workers may be brought on site, and it is not unusual for staff to more than triple. Outages cluster in the first quarter and the fall, when demand is seasonally lowest. The plant is a different organisation for those weeks, and the EIA is explicit that the event is a planned exception, not the operating norm.

The skill mix differs too. Turnaround work runs on contract labour, which brings boilermakers, pipefitters, scaffolders and riggers who will not be there next month. In India's organised manufacturing, contract workers now account for 42% of employees, the highest share since 1997-98, according to Annual Survey of Industries data. A plant with that workforce structure has, in effect, two training populations: a stable core and a rotating contract body whose needs are specific, real, and mostly not about the plant at all.

So the first question is not who is available. It is which states of operation does this workforce actually do, and for how long in each.

Start from the production calendar, not the HR list

Build a state calendar before writing a single question. Four states cover most process and manufacturing plants: running at normal load, running at peak, planned shutdown or turnaround, and startup after shutdown. Add a fifth only if it is materially different, such as a statutory inspection window or a product changeover with its own skill set.

For each state, get two numbers from records you already own: hours per year in that state, and the distinct people present during it. Take the hours from the production plan and the utility logs, not from a guess. Take the headcount from the gate register, deployment list and shift roster for the same window, because during a shutdown the HR roster is the least accurate of the three.

Multiply to get exposure in person-hours. That single column reorders the whole TNA.

StateHours per yearPeople presentExposure (person-hours)Share
Running, off-peak5,4002001,080,00059.7%
Running, peak2,000200400,00022.1%
Planned shutdown430700301,00016.6%
Startup after shutdown6047028,2001.6%

The numbers are illustrative, but the shape repeats: the shutdown has 3.5 times the headcount of normal operation and 8% of the hours, so it carries under a fifth of the exposure. A fieldwork plan that puts all its interviews in shutdown week has sampled 17% of the year's exposure and reported it as the whole.

Turn exposure into observation counts

Now size the fieldwork. Work sampling gives the arithmetic for how many observations a proportion needs at a stated precision: n = z² p (1-p) / e², where z is 1.96 at 95% confidence, p is the proportion of time an activity occupies, and e is the margin in proportion points. At p = 0.3 and a 5-point margin, that is about 323 observations in total.

Sizing on p alone gets you one number for the whole plant. Allocate it across states in proportion to exposure, then check that no state falls below a floor. A state with 1.6% of exposure will receive an allocation too small to say anything about it, and the states with the rarest, most dangerous work are often exactly those. Set a floor of 40 observations per state and take the difference from the largest state.

StateExposure shareAllocation of 600Margin at p = 0.3
Running, off-peak59.7%327±4.9 points
Running, peak22.1%133±7.8 points
Planned shutdown16.6%100±9.0 points
Startup after shutdown1.6%40±14.2 points

Read the margins honestly. The shutdown cell now supports a statement to within nine points, which is enough to rank a competency as common or not. The startup cell supports only a coarse statement, and the plan should say so rather than printing it as a percentage.

Two things follow. First, the shutdown gets 100 observations, not 600, so the fieldwork cannot be done in one week. It runs across at least one shutdown and one peak period, and the second period may be six months away. Second, the report has to carry weights. If 40 startup observations and 327 off-peak observations are pooled without a weight, the answer describes the fieldwork plan, not the plant.

Collect in the state you are asking about

Observation counts decide where the hours go. The questions decide what comes back, and their wording has to hold the state fixed.

Critical incident technique, the structured interview that asks for specific past events rather than opinions, is the standard instrument here, and it has a known failure: it relies on the respondent's memory of events, so recent and dramatic incidents crowd out routine ones. The practical rule is to cap the recall window at about 90 days and to accept a report only from someone who was in the state being asked about.

That means the interview protocol splits by state:

  • For running states, ask for the last three occasions the operator caught a deviation before it became a trip. Cap at 90 days.
  • For the shutdown, ask the planning question, not the running question: what did the job plan not tell you, and who did you have to ask. Collect from own staff and from the contractor supervisor separately, because they hold different halves of the answer.
  • For startup, ask for the last two startups and what went wrong between first feed and stable operation. This is the state most often skipped, and the one where the crew is running plant it has not touched for a year.
  • For contractors, ask about induction, permit reading and isolation verification. Their need is not "understand our plant", it is "be able to work safely in a plant you have never seen", which is a different curriculum.

Verify that people were actually in the state they report. A gate register or shift roster will show whether the fitter who described a compressor trip in March was on site in March. Where the record and the memory disagree, keep the case and mark the disagreement. Do not silently drop it, and do not resolve it by asking the supervisor to confirm.

A worked example, with weights

Take the plant above and say the TNA returns 600 incident interviews: 327 from running off-peak, 133 from peak, 100 from shutdown, 40 from startup. Of the 100 shutdown interviews, 61 name isolation verification as a gap. Of the 327 off-peak interviews, 22 do. Of the 40 startup interviews, 24 name it.

Unweighted, the pooled rate is 107/600, or 17.8%. That number is meaningless: it is dominated by whichever cell was sampled hardest.

Weighted by exposure share, the estimate is 0.597 × 6.7% + 0.221 × (peak cell rate) + 0.166 × 61% + 0.016 × 60%. With the peak cell at 8%, that is 4.0 + 1.8 + 10.1 + 1.0, or about 17% of exposure-weighted time in which isolation verification is a live gap. The headline barely moves, and the diagnosis changes completely: the gap is concentrated in one state, at one site of control, for one audience. The correct response is three days of isolation and lock-out training delivered at the gate at the start of every turnaround plus a refresher inside the operator certification, not a plant-wide programme for 700 people.

That distinction is what the shutdown-only TNA could not produce. It reported 61% and recommended a plant-wide campaign, because 61% of its sample said so and its sample was the shutdown.

The honest limit

Exposure weighting is not free and it is not always right. It overweights long shifts and large crews, so a state with a big contractor body can pull the result toward work that is brief in skill terms. It also assumes the states are internally similar, which fails if one unit runs while the rest is down. And it needs records that many sites do not keep cleanly: hours by state and headcount by state are exactly the two numbers that plant reporting systems usually hold in different places.

If the calendar is genuinely unavailable, the fallback is to sample the state with the largest exposure, state the bias in the report in one sentence, and shrink the claim to that state. What you must not do is sample by convenience and present the result as the plant.

The other limit is time. A four-state design usually needs two fieldwork windows separated by months, which is slower than the December week everyone prefers. That cost is real, and it is smaller than the cost of a training year aimed at an audience that left in January.

What to do before the next shutdown

Pull the last twelve months of production and utility logs, and count the hours this plant spent running, at peak, down and starting up. Then pull the gate register for the same period and count distinct people in each state. Multiply, and look at the exposure column. If the shutdown holds less than a quarter of the year's exposure, your next TNA cannot be run during it.

Book the two fieldwork windows now, before the shutdown dates are fixed, so the calendar forces the design instead of the design chasing the calendar. When the findings land, the analysis-to-plan step is where the weights get lost, because a plan written from pooled counts drops the state column. The one-page TNA brief is a good place to record which exposure share each finding came from, and what the platform tracks keeps the state tag attached to every competency so the weights survive into next year's cycle. Before you build any of it, check the roster against payroll and the gate, because a wrong population makes an exposure weight a confident statement about the wrong people.

Next step

Run the same measurement on your own team

Bring a real team and a real competency. We set up the assessment, run one cycle, and walk you through the report so you can judge the output yourself.

Written by

Rajendra Kumar

Head of Enterprise Business, Conceptial

Runs enterprise work at Conceptial, the training and consulting firm behind BolderBrain. Two decades of building assessment and development programmes for Indian enterprises.